Series · 13 parts · Grid & storage

The Grid Build-Out

The ₹9.15 lakh crore transmission question, and the state-level equity deficit hiding inside it.

RK

R. K. Mundoli

Director — Projects & Advisory, Terrastrom Solutions

August 2026 · 7 min read · Part 11 of 13

25 years across the renewable value chain; 1,700 MW of independent diligence; lead developer of the 5 GW KREDL hybrid DPR.

India added 242.49 GW of peak demand in 2026 with a shortage of just 0.03%. That headline is deceptively comfortable. It was achieved on a grid built for fossil fuels — not for 500 GW of wind and solar scattered across the country’s sun-rich periphery. The ₹9.15 lakh crore grid build-out is not a capital-markets problem alone. It is the country’s deepest ethical infrastructure test: will the transmission system carry clean power to every consumer, or will it route prosperity along the same lines it always has?

⚠ The grid that carries India’s green transition is not the grid India currently has.

Building it will cost ₹9.15 lakh crore. The financing architecture is coherent.

The equity gap is not. And that gap has a name: the State-Level Equity Deficit.

The ₹9.15 lakh crore question

01 · THE SIZE OF THE ASK

₹9.15 lakh crore — and why the number understates the challenge

The CEA’s National Electricity Plan sets the figure plainly: ₹9.15 lakh crore of new transmission investment is needed between now and 2032. That is more than the annual revenue of many mid-sized economies — spent not on generating power, but on the wires that carry it. The scale reflects a structural mismatch in the geography of India’s energy transition.

India’s renewable energy potential is concentrated where land is plentiful: Rajasthan, Gujarat, Tamil Nadu, Karnataka, Andhra Pradesh. India’s load is concentrated where industry and population are dense: Maharashtra, Uttar Pradesh, Delhi, West Bengal. The transmission network is the bridge between these two geographies. Without it, the ~23 GW of curtailed renewable capacity recorded in 2025 does not resolve — it compounds.

The ₹9.15 lakh crore disaggregates four ways:

▸ Jurisdictional split — ISTS (inter-state) 60% of total investment; InSTS (intra-state) 40%.

▸ Execution mode — TBCB (Tariff-Based Competitive Bidding) 65%; RTM (Regulated Tariff Mechanism) 35%.

▸ Capital structure — 70% debt, 30% equity across the portfolio.

▸ Debt sourcing — PFC/REC/NaBFID anchor 45–50%; commercial banks/InvITs 25–30%; World Bank/ADB/KfW 20–25%.

02 · ISTS — THE LONG-DISTANCE SPINE

POWERGRID, TBCB, and the Green Energy Corridors

POWERGRID leads the ISTS build. The Green Energy Corridors (GEC) Phases I and II are the proof of concept: HVDC and high-voltage AC lines running from Rajasthan’s solar parks and Tamil Nadu’s wind farms to the northern and western demand centres. GEC Phase I (33 GW evacuation capacity) was commissioned by 2022. Phase II — 20 GW across seven renewable energy zones — is under construction.

TBCB is the preferred execution mode. Private developers — Adani Transmission, Sterlite Power, Torrent Power — win 35-year concessions against a levelised tariff under the CERC framework. The 65% TBCB share means private capital is already the primary builder of the transmission backbone. The state does not write the construction cheque.

TBCB carries a structural tension, however. Developers bid aggressively to win, then file tariff revision petitions when costs escalate during construction. The CERC has held a firm line, but the growing backlog of revision petitions is a lagging indicator of whether competitive discipline can hold at ₹9.15 lakh crore scale.

03 · InSTS — WHERE EQUITY LIVES

The State-Level Equity Deficit: the systemic bottleneck

InSTS — the intra-state lines owned and built by State Transmission Utilities (STUs) — is 40% of total investment: roughly ₹3.66 lakh crore. It is also where the system carries its greatest ethical weight.

ISTS moves electrons between states. InSTS moves electrons to the consumer. A solar park in Rajasthan that pumps power onto the ISTS backbone is operationally irrelevant to a household in rural UP if the InSTS lines that should carry it to the feeder are overloaded or absent. The last ethical mile of the energy transition runs through state-owned infrastructure.

STUs are owned by state governments whose balance sheets are already stretched. DISCOM debt stands at ₹1.24 lakh crore under UDAY data. States are simultaneously expected to fund their share of RDSS (the ₹75,021 crore distribution upgrade scheme) and their share of InSTS equity. The arithmetic does not close.

Total portfolio equity is approximately ₹2.75 lakh crore (30% of ₹9.15 lakh crore). The Centre and POWERGRID can credibly deploy roughly half — around ₹1.37 lakh crore. The remaining ~₹1.37 lakh crore must come from states and STUs. For most states in eastern and central India, this is not feasible without central equity support, co-investment vehicles, or multilateral concessional loans.

The State-Level Equity Deficit is not a moral failure — it is an arithmetic one. But it has moral consequences. The states that fall behind on InSTS investment are, by definition, the states that fail to deliver clean power to the consumers who have waited longest.

[FRAMEWORK]

The ₹9.15 lakh crore transmission investment — four-way disaggregation:

Jurisdictional: ISTS ₹5.49 lakh crore (60%) | InSTS ₹3.66 lakh crore (40%)

Execution: TBCB ₹5.95 lakh crore (65%) | RTM ₹3.20 lakh crore (35%)

Capital structure: Debt ₹6.41 lakh crore (70%) | Equity ₹2.75 lakh crore (30%)

Equity split: Centre/POWERGRID ~₹1.37 lakh crore | States/STUs ~₹1.37 lakh crore

Debt sourcing: PFC/REC/NaBFID 45–50% · Banks/InvITs 25–30% · World Bank/ADB/KfW 20–25%

The State-Level Equity Deficit — the gap between the ~₹1.37 lakh crore states must deploy

and what their constrained balance sheets can support — is the single largest systemic risk

to the transmission build-out timeline and the primary driver of InSTS under-investment.

Source: CEA National Electricity Plan 2022–27 and 2027–32.

04 · THE FINANCING STACK

PFC, NaBFID, multilaterals, and the InvIT recycling engine

PFC and REC are the primary lending vehicles, with combined loan books already exceeding ₹9 lakh crore. They can absorb the ISTS tranche. NaBFID adds a new instrument for longer-tenor, infrastructure-grade paper that commercial banks have historically declined to hold.

The multilateral tranche (20–25% of debt) carries covenants that matter ethically. World Bank, ADB, and KfW loans to POWERGRID and STU vehicles require environmental and social safeguards, independent monitors, and functioning grievance redress mechanisms — the closest the sector has to a structured rights-protection mechanism for transmission corridors crossing agricultural and forest land.

InvITs (Infrastructure Investment Trusts) are the secondary market instrument that makes the recycling engine work. Once a corridor is commissioned under a 35-year TBCB concession, the developer securitises it into a listed InvIT, recycles equity, and redeploys capital into the next corridor. Without active InvIT recycling, developers hit balance-sheet limits well before 2032 and the TBCB pipeline stalls.

05 · THE ETHICAL GEOMETRY OF TRANSMISSION PLANNING

Who gets the wire — and who decides

Transmission planning is not neutral. Every route decision routes economic benefit. An ISTS corridor optimised for least-cost power flow may bypass districts with unmet demand and no political weight to redirect the line. ISTS planners optimise for system economics; InSTS planners optimise for state fiscal comfort. Neither framework has an explicit criterion for energy access equity.

The RDSS addresses distribution — the last 11 kV before the meter. But distribution upgrades are irrelevant if the 400 kV InSTS backbone that feeds them is not built. The ethical chain runs unbroken: ISTS spine → InSTS corridor → distribution feeder → household meter. A gap anywhere severs the whole.

The green transition is institutionally constrained, not technologically constrained. That is the central verdict of this series. The technology to build the grid exists. The financing architecture to fund it exists. The institutional capacity to allocate equity fairly, plan routes with explicit access criteria, and hold states accountable for InSTS delivery — that is the variable. And it is the one the market does not provide.

The ₹9.15 lakh crore will be found — the capital architecture is coherent and the financing vehicles are in place. What remains open is not whether the grid gets built, but which consumers it reaches first, and which ones wait another decade. That is a planning choice, not a market outcome. It is being made now, in the rooms where ISTS route alignments are drawn and InSTS equity allocations are negotiated. If those choices are not made with explicit equity criteria, the grid will be technically successful and socially incomplete — and the 500 GW target will be a number that hides the households it left behind.

→ · COMING UP IN PART 12


Part 12 — The Blind Spots and the Final Verdict — examines the three institutional risks held back for the closing argument: Just Transition for coal workers in Jharkhand and Odisha, Critical Minerals dependency and the Reasi lithium discovery, and the Water-Energy Nexus. It closes with the series verdict: the green transition is institutionally constrained, not technologically constrained.

#EthicsofGridStability #RenewableEnergy #IndianRESector #IPP #Governance #Sustainability #ISO #EnOS #SupplyChain #TechnicalSentinel

Related work

We do this for a living, not only in writing.

Grid and evacuation design to 400 kV, storage sizing on hybrid programmes, and 1,700 MW of independent generation and grid evaluation for investors and lenders.